| SUNDAY | MONDAY | TUESDAY | WEDNESDAY | THURSDAY | FRIDAY | SATURDAY | |
|---|---|---|---|---|---|---|---|
1 |
2 |
||||||
|
|
|
|
|
|
||
3 |
4 |
5 |
6 |
7 |
8 |
9 |
|
|
|
|
|
|
|
|
|
10 |
11 |
12 |
13 |
14 |
15 |
16 |
|
|
|
|
|
|
|
||
17 |
18 |
19 |
20 |
21 |
22 |
23 |
|
|
|
|
Travel Day (Leads) |
Travel Day
Leads(Volunteers) Layout & Build Components Meet & Greet |
Build & Set walls Roll Trusses |
Finish Rolling Trusses Install Roof Decking & Paper |
|
24 |
25 |
26 |
27 |
28 |
29 |
30 |
|
|
Day of Rest
Team Dinner |
Subs Inside Ext. Doors & Windows Inspection Start Shingles Start Siding |
Insulation Drywall |
Siding Roofing Painting Interior Trim After work group activity |
Finish painting and interior trim, install cabinets/counter tops, porch rails, floor covering |
Carpet Landscape Closet Hardware Touch-up Paint Finish trim |
House Dedication (morning) |
Detailed Contruction Schedule (Tentative)